How do the DCO examination hearings work?

DCO Examination

The UK Planning Inspectorate appointed a panel of inspectors, known as an Examining Authority (ExA), to review the application on behalf of the UK Secretary of State for Business, Energy and Industrial Strategy.

The ExA ran the preliminary meeting on 20th September, with other hearings scheduled to discuss specific issues relating to our proposals

The examination then concluded at 23:59 on 20 March 2023.

Hearings focus on fact-finding without pitting one side against another and, whilst the hearings are important, the examination process is primarily a written one. All documents are  published on the UK Planning Inspectorate’s website (Awel y Môr Offshore Wind Farm | National Infrastructure Planning (planninginspectorate.gov.uk) – please refer to ‘Examination’ header on LHS of ‘Documents’ page)

Below is some information which we hope you will find useful.

 

Public Hearings

DCO Examination

The first public hearings into the Awel y Môr project took place on 21st and 22nd September 2022.

These hearings took place at Venue Cymru, Llandudno, and were open to anyone to attend.

An audio recording and notes of the first meetings has been made available on the UK Planning Inspectorate’s project webpage Awel y Môr Offshore Wind Farm | National Infrastructure Planning (planninginspectorate.gov.uk)

Other hearings took place on 7th and 8th of December 2022, on 28 February 2023, and 1 March 2023.

There was also an accompanied site inspection on 6th December 2022.

 

What happened and who got to speak at hearings?

DCO Examination

Topics, and the names of those requested to attend or answer written questions, were published in advance of each hearing on the UK Planning Inspectorate’s website.

‘Interested Parties’ who registered ahead of time, by making a ‘relevant representation’, and statutory bodies, including the relevant regulators, were also invited to contribute.

People who are not registered as Interested Parties are not automatically entitled to participate, but the panel may permit them to do so.

Advice was provided on the registration process in previous newsletters, and you can find out more about involvement in the Examination through the UK Planning Inspectorate’s website.

How do the hearings fit into the process?

DCO Examination

The UK Planning Inspectorate had six months to carry out its examination of our application for a Development Consent Order (DCO).

Following the conclusion of the examination, the Examining Authority is to send its findings and conclusion, alongside a recommendation to the Secretary of State for Energy Security and Net Zero no later than 20 June 2023.

The Secretary of State then has a further three months to make a decision.

What did the Examining Authority decide will be covered?

DCO Examination

• Aviation
• Biodiversity, ecology & natural environment
• Commercial uses of the sea such as shipping, navigation, fisheries
• Compulsory acquisition and temporary possession of land
• Construction
• The draft DCO
• Flood risk and water quality
• The effect on the natural marine environment
• Good design
• Historic environment
• Land use

Seascape, landscape and visual impact
• Marine & coastal physical processes
• Commercial uses of the sea such as shipping, navigation, fisheries.
• The effect on the natural marine environment
• Other projects and proposals nearby
• Public health and nuisance
• Other projects and proposals nearby
• Project description and site selection
• Seascape, landscape and visual impact
• Socio-economics
• Tourism & recreation
• Traffic & transport