We received our Contract for Difference (CfD) as part of Auction Round 7 in January 2026. The project team is now working towards its final investment decision (FID).
The project received its Development Consent Order and our marine licences in 2023, approving a maximum number of turbines of between 34 and 50.
In 2024 we carried out extensive surveys on ground conditions, both offshore and along the project’s cable route. Archaeological investigations were also undertaken at the proposed substation site, along with mitigation work for great crested newts, including creating a new habitat for this important protected species.
The project is currently preparing for its final investment decision (FID).
Key elements of the project that have now been defined include the offshore cable corridor, cable landfall location, the onshore cable corridor, potential sites for temporary construction compounds, and the substation location.
Some aspects of detailed design such as the design of the onshore substation and number and dimensions of turbines, are still being developed, with details to be confirmed as we reach FID.